Kitui Water Projects

Water Projects to be Supported by Friends of Kitui in 2006/2007

Project No: 5

Project Name Ngathano Subsurface dam
Location:   Kithumula which is 26 km North of Kitui town

Description:

This  project will serve a big community. People have depended on wells at the centre of this seasonal river which became too deep during dry Months.

Community Group

This Project has been proposed by the Ngathano Community Group

Community Background

Most of the members of the Ngathano group are involved in Kitchen gardening, waving baskets & selling of sisal fibres

 

Group Details

No. Of Members

70 families

Chairman

Beatrice Kimotho

Beneficiaries

This project will supply water for a total of 560 people including children and dependants

Project Cost

The total cost of this project will be €5,655                                                 

Community’s own Contribution

 €2,507 in local labour and materials

External Funding Required  for materials & Supervision

Materials & Skilled Labour

 €2,500

Diocesan Management Cost

   €647

Total Partner Contribution

€3,148 for materials not available locally & for the management and supervision of the work

Project Status

Technical Assessment Completed

YES

 

 

 

Approved by Diocesan Water Department on

10th May 2006

Project Duration

150 Days approximately

Start Date

Provisionally 1st June 2006- waiting for funds

Benefits  

On completion, this project will provide the following benefits for the community:

Walking distance to water source will be reduced, and so Mothers will have time to attend to young children, and more time will be available for Farming, soil conservation, and building schools. School going children will have more time for their studies. Group members will have more plentiful, and cleaner water than before.

Comments

This is a good site and needs to be worked on before the November rains.

 

NGATHANO SUBSURFACE DAM Phase 1

Partner Contribution
NO DESCRIPTION UNIT Qty. UNIT COST TOTAL COST Euro
1 Ordinary portland cement Bags 144 KES 645.00 KES 92,880.00 €1,161.00
2 Soft wood timber 10x1 R/ft 216 KES 37.00 KES 7,992.00 €99.90
3 Soft wood timber 4x2 R/Ft 108 KES 25.00 KES 2,700.00 €33.75
4 Round wire nails 3’ Kg 4 KES 80.00 KES 320.00 €4.00
5 Used engine oil Lt 20 KES 20.00 KES 400.00 €5.00
6 Crow bar 6ft long No. 2 KES 650.00 KES 1,300.00 €16.25
7 Sledge harmer 12Lbs No. 2 KES 1,200.00 KES 2,400.00 €30.00
8 Mason hammer 2.5lb No. 3 KES 400.00 KES 1,200.00 €15.00
9 Shovels No. 5 KES 250.00 KES 1,250.00 €15.63
10 Wheelbarows No 2 KES 2,500.00 KES 5,000.00 €62.50
11 Building karais No. 6 KES 200.00 KES 1,200.00 €15.00
12 Muttock No 4 KES 500.00 KES 2,000.00 €25.00
13 Machette No. 1 KES 400.00 KES 400.00 €5.00
14 3 artisans at KES300/day Days 90 KES 900.00 KES 81,000.00 €1,012.50
M DOK Management cost       KES 51,800.00 €647.50
Sub-total KES 251,842.00 €3,148.03
Community Contribution
15 Ballast Ύ dia Ton 29 KES 1,400.00 KES 40,600.00 €507.50
16 Sand Ton 24 KES 500.00 KES 12,000.00 €150.00
17 Hardcore Ton 8 KES 500.00 KES 4,000.00 €50.00
18 8 Unskilled artisans Days 120 KES 1,200.00 KES 144,000.00 €1,800.00
Sub-total KES 200,600.00 €2,507.50
Total Project Cost KES 452,442.00 €5,655.53