Water Projects to be Supported by Friends of Kitui  in 2006/2007  

Project No: 1

Project Name Miaani Well Rehabilitation
Location Mutito which is 80 km East  from Kitui town
Description This project is for the reconstruction of an existing well. It needs deepening to increase discharge and an AfriDev hand pump is needed to cope with the depth. In a very dry area.
Community Group   This Project has been proposed by the Kyeni kya Miaani Community Group
Community Background   Most of the members of the Kyeni kya Miaani group are involved in peasant farming and few keep indigenous animals and burn charcoal for sale.
Group Details   No. Of Members 35 Families (280 people)
Chairman Musyoka Musya
Beneficiaries   This project will supply water for a total of 280 people including children and dependants
Project Cost   The total cost of this project will be  €1873.00
Community’s own Contribution   €424 in local labour and materials
External Funding Required  for materials & Supervision   Materials & Skilled Labour €802
Diocesan Management Cost €647
Total Partner Contribution   €1,450 for materials not available locally & for the management and supervision of the work
Project Status   Technical Assessment Completed YES
Approved by Diocesan Water Department on 6th May 2006
Project Duration   45 days approximately
Start Date   Provisionally 30th May 2006- awaiting funding

Benefits  

On completion, this project will provide the following benefits for the community:

 

Walking distance to water source will be reduced,

Mothers will have time to attend to young children, Time will be created for school going children, Group members will get cleaner water than before for their domestic use.

Comments   There is an urgent need to rehabilitate this well.

Cost Breakdown:

KYENI KYA MIAANI WELL REHABILITATION

Partner Contribution
Item DESCRIPTION UNIT Qty. UNIT COST TOTAL COST Euro
1 Ordinary portland cement Bags 11 KES 645.00 KES 7,095.00 €88.69
2 Afri-dev pump Set 1 KES 45,000.00 KES 45,000.00 €562.50
3 Well deepening Ft 10 KES 800.00 KES 8,000.00 €100.00
4 Installation Ls 1 KES 1,200.00 KES 1,200.00 €15.00
5 Steel bucket No. 1 KES 300.00 KES 300.00 €3.75
6 Cold chisel No. 1 KES 720.00 KES 720.00 €9.00
7 Nylon rope M 40 KES 20.00 KES 800.00 €10.00
8 Shovel No. 1 KES 250.00 KES 250.00 €3.13
9 Karai No. 2 KES 200.00 KES 400.00 €5.00
10 Mason hammer No 1 KES 400.00 KES 400.00 €5.00
M DOK Management cost       KES 51,800.00 €647.50
Sub-TOTAL KES 115,965.00 €1,449.56
Community Contribution
11 Ballast Ton 1 KES 1,400.00 KES 1,400.00 €17.50
12 Sand Ton 1 KES 500.00 KES 500.00 €6.25
13 Hardcore Ton 1 KES 500.00 KES 500.00 €6.25
14 Board & lodge artisans Days 36 KES 250.00 KES 9,000.00 €112.50
15 4 Unskilled laborers Days 36 KES 625.00 KES 22,500.00 €281.25

Sub-TOTAL

KES 33,900.00 €423.75
Total Project Cost KES 149,865.00 €1,873.31